New Trier High School
Winnetka, IL.
268,000 square foot addition consisting of 4 stories with a lower level, including classrooms, fine arts and an auditorium.
Contract: $9,102,400
Construction Manager/GC:
Pepper Construction
Architect/Engineer:
Wight Construction Services
True Value Corporate Office, Chicago IL.
Details coming soon.
Officite
Downers Grove, IL
The project included a tenant improvement.
Contract: $ 400,000
Construction Manager/GC:
Tannco Construction
Architect/Engineer:
Tannco Construction
Batavia High School
Batavia, IL
Project comprised of an Auditorium and Fieldhouse addition, along with a renovation of the existing High School.
Contract: $4,050,400
Construction Manager/GC:
Lamp Incorporated
Architect/Engineer:
Arcon Associates
Fort Hill Activity Center
Naperville, IL
80,000 square foot new fitness/activity center.
Contract: $1,825,125
Construction Manager/GC:
Wight Construction Service
Architect/Engineer:
Williams Architects
Tioga Elementary School
Bensenville, IL
86,000 square foot two-story addition to the existing Elementary School.
Contract: $2,092,000
Construction Manager/GC:
Gilbane Building Company
Architect/Engineer:
STR Partners LLC
IDOT Maintenance Facility Eisenhower Parkway
Chicago, IL
The Construct Maintenance Facility project on the Eisenhower Parkway is a 28,000 square foot new IDOT facility.
Contract: $506,550
Construction Manager/GC:
Illinois Capital Development Board
Architect/Engineer:
Wold Architects/Engineers
College of DuPage
Homeland Security
Training Center
40,000 square foot new training facility; included a shooting range, classrooms, and a virtual reality simulator.
Contract: $ 1,808,095
Construction Manager/GC:
Power Construction Company
Architect/Engineer:
Legat Architects
Hubble Middle School
Wheaton, IL
190,000 square foot new school facility with an auditorium.
Contract: $ 3,550,000
Construction Manager/GC:
Bovis Lend Lease
Architect/Engineer:
Arcon Associates
Confidential Client
Montgomery, IL
Electrical upgrade for a manufacturing facility.
Contract: $ 2,982,385
Construction Manager/GC:
Kluber Architects + Engineers
Architect/Engineer:
Kluber Architects + Engineers
Molex Corporation
Lisle, IL
New Construction Project involved adding an addition to the facility. The second Molex Corporation project consisted of a cafeteria remodel.
Contract: $ 3,625,585
Project 1
Construction Manager/GC:
Novak Construction
Project 2
Construction Manager/GC:
Edison Construction Company
Architect/Engineer:
Robert Varnes & Associates
Richard Edwards
Elementary School
Chicago, IL
50,200 square foot addition to the existing Chicago Public Elementary School.
Contract: $2,225,350
Construction Manager/GC:
Berglund Construction
Architect/Engineer:
STL Architects